Sir Robert McAlpine – The Royal Albert Hall
Development work is being carried out ahead of the Hall’s 150th birthday, which will fall on 29 March 2021. The Royal Albert Hall hosts almost 400 events a year; more than one each day.
Sir Robert McAlpine – The Royal Albert Hall
Start Date
November 2018Client
Sir Robert McAlpineProject Type
Mechanical, Plumbing & Heating, ElectricalLocation
London
Project Scope
The Finer Details
Services implemented
we are replacing the old steam boiler plant room with a new gas fired boiler plant room and providing a new staircase for public access, which includes renovating a changing room and 2 toilets
- Low temperature hot water
- Chilled water
- Rainwater goods
- Soil and vent
- Domestic hot and cold water
- Sprinkler system
- Gas
- BMS
- Fire alarm
- Security and access control
- Lighting
- Small power
- Main low voltage panel
- Main distribution system
- Containment
- Data
- Mechanical design verification
- Electrical design verification